Stay tuned with our progress as we turn the bond into bricks and diligently work to improve our learning facilities for students all across the Killeen Independent School District. This website will be updated regularly in order to keep our community informed as to how their bond dollars are being responsibly stewarded. In May 2018, voters overwhelmingly approved both propositions of the new May 2018 Bond Election, which will allow the district to invest $426 million to provide new schools for growth, critical safety and accessibility improvements district wide, and replacement and renovation of our oldest campuses.

News and Updates

KISD High School #6

Artist Rendering Of Main Entrance

KISD High School #6
Date Added: 11/02/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/2018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 11/02/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK received direction to proceed with presenting Option 3C to the School Board.
  2. PBK investigating temp kitchen/seating layout. Providing sketch for review on 11/02/2018.
Read More
KISD High School #6

Fine Arts Entrance

KISD High School #6
Date Added: 10/26/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.