Stay tuned with our progress as we turn the bond into bricks and diligently work to improve our learning facilities for students all across the Killeen Independent School District. This website will be updated regularly in order to keep our community informed as to how their bond dollars are being responsibly stewarded. In May 2018, voters overwhelmingly approved both propositions of the new May 2018 Bond Election, which will allow the district to invest $426 million to provide new schools for growth, critical safety and accessibility improvements district wide, and replacement and renovation of our oldest campuses.

News and Updates

KISD High School #6
KISD High School #6
Date Added: 03/15/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. KISD / Bell County / City of Harker Heights / City of Killeen meetings regarding Chaparral Road took place on 12/7/17, 5/30/18, 8/8/18, 11/28/2018, 01/23/2019, 01/31/2019 and 02/27/2019.
  2. DBR Engineering has been selected as Commissioning Agent for KISD HS#6.
  3. Preliminary finished review meeting took place 02/15/2019 at 2:00 PM.
  4. American Constructors budget review meeting took place 03/06/2019 at 4:30 PM.
Read More
General Updates
General Updates
Date Added: 03/06/19
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • The project has transitioned from the Design Development phase to the Construction Document phase and is currently on schedule.
Read More
KISD High School #6
KISD High School #6
Date Added: 03/01/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. KISD / Bell County / City of Harker Heights / City of Killeen meetings regarding Chaparral Road took place on 12/7/17, 5/30/18, 8/8/18, 11/28/2018, 01/23/2019, 01/31/2019, and 02/27/2019.
  2. DBR Engineering has been selected as Commissioning Agent for KISD HS#6.
Read More