Category - General Updates

General Updates
General Updates
Date Added: 03/06/19
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • The project has transitioned from the Design Development phase to the Construction Document phase and is currently on schedule.
Read More
General Updates
General Updates
Date Added: 01/24/19
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • At the December Board Meeting, the Board of Trustees approved a change to the exterior design of the prototype building to be more equitable to the most recent KISD school designs. See attached.
  • Design Development documents are in production.
Read More
General Updates
General Updates
Date Added: 01/13/19
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • At the December Board Meeting, the Board of Trustees approved a change to the exterior design of the prototype building to be more equitable to the most recent KISD school designs. See attached.
  • Design Development documents are in production.
Read More
General Updates
General Updates
Date Added: 11/30/2018
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • Schematic Design was presented to the Board of Trustees on Tuesday. Board members provided valuable feedback and expressed positive support for the design of the building. The project goes to the board on Dec. 11 for approval of the Schematic Design phase.
Read More
September 14, 2018 Meeting Minutes
October 05, 2018 - Meeting Minutes
Date Added: 10/05/18
Item Update Items
1 General
2 Pershing Park/Sugar Loaf/Bellaire
  • After further analysis of student capacity needs, KISD chose to change the design of the Pershing Park/Sugar Loaf/Bellaire project to a 2-story 1,050 student facility. The schedule for the project is being revised based on a Fall 2021 opening date.
Read More
September 28, 2018 - Meeting Minutes
September 28, 2018 - Meeting Minutes
Date Added: 09/28/18
Item Update Items
1 General
2 East Ward/ West Ward
  • The design team presented the Schematic Design package to the Board of Trustees. Board members provided valuable feedback and expressed strong support for the design of the building.
Read More
September 14-2018 Meeting Minutes
September 14, 2018 Meeting Minutes
Date Added: 09/14/18
Item Update Items
1 General
2 Pershing Park/ Sugar Loaf /Bellaire
  • The design team met with district leadership to review options and determine a palette for the interior materials and colors.

Read More
Bond Program Is Well Underway
Bond Program Is Well Underway
Date Added: 08/10/2018

The Killeen ISD’s Bond Program is well underway, on budget and in some cases, projects have moved up in schedule. In May 2018, this community overwhelmingly authorized the school district to invest $426 million...

Read More
August 02-2018 Meeting Minutes
August 02, 2018 Meeting Minutes
Date Added: 08/02/2018

Project Name: Killeen High School Renovation & Modernization
Current Phase: Construction Administration
Contractor: TBD

Read More
July 27-2018 Meeting Minutes
July 27, 2018 Meeting Minutes
Date Added: 07/27/2018
Item Update Items
1 General
  • The East Ward/West ES and Pershing Park/Sugar Loaf/Bellaire ES projects are off and running! Nearly two dozen members of KISD leadership kicked the Huckabee team off with an inaugural project review session for the two projects that looked that the spaces that the building will contain along with the challenges and opportunities with each existing site.
  • KISD is evaluating geotechnical proposals for the East Ward/West Ward ES and Pershing Park/Sugar Loaf/Bellaire ES projects.

Read More