Category - KISD HS #6

KISD High School #6
KISD High School #6
Date Added: 03/15/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. KISD / Bell County / City of Harker Heights / City of Killeen meetings regarding Chaparral Road took place on 12/7/17, 5/30/18, 8/8/18, 11/28/2018, 01/23/2019, 01/31/2019 and 02/27/2019.
  2. DBR Engineering has been selected as Commissioning Agent for KISD HS#6.
  3. Preliminary finished review meeting took place 02/15/2019 at 2:00 PM.
  4. American Constructors budget review meeting took place 03/06/2019 at 4:30 PM.
Read More
KISD High School #6
KISD High School #6
Date Added: 03/01/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. KISD / Bell County / City of Harker Heights / City of Killeen meetings regarding Chaparral Road took place on 12/7/17, 5/30/18, 8/8/18, 11/28/2018, 01/23/2019, 01/31/2019, and 02/27/2019.
  2. DBR Engineering has been selected as Commissioning Agent for KISD HS#6.
Read More
KISD High School #6
KISD High School #6
Date Added: 02/15/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. KISD / Bell County / City of Harker Heights / City of Killeen meetings regarding Chaparral Road took place on 12/7/17, 5/30/18, 8/8/18, 11/28/2018, 01/23/2019, and 01/31/2019.
  2. PBK Sports / Killeen ISD athletics review meeting took place Wednesday, 01/30/2019 at 10:00 AM at KISD Facilities conference room.
Read More
KISD High School #6
KISD High School #6
Date Added: 02/08/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. KISD / Bell County / City of Harker Heights / City of Killeen meetings regarding Chaparral Road took place on 12/7/17, 5/30/18, 8/8/18, 11/28/2018, 01/23/2019, and 01/31/2019.
  2. PBK Sports / Killeen ISD athletics review meeting took place Wednesday, 01/30/2019 at 10:00 AM at KISD Facilities conference room.
Read More
KISD High School #6
KISD High School #6
Date Added: 01/25/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
  3. Schematic Design presentation and Board of Trustees approval took place 10/09/2018.
Read More
KISD High School #6
KISD High School #6
Date Added: 01/11/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
  3. Schematic Design presentation and Board of Trustees approval took place 10/09/2018.
Read More
KISD High School #6

Fine Arts Entry View

KISD High School #6
Date Added: 01/11/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
  3. Schematic Design presentation and Board of Trustees approval took place 10/09/2018.
Read More
KISD High School #6

Fine Arts & Athletics Entry View

KISD High School #6
Date Added: 01/04/19
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
Read More
KISD High School #6

Fine Arts & Athletics Entry View

KISD High School #6
Date Added: 12/21/2018
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
Read More
KISD High School #6

Checking depth of test pit one

KISD High School #6
Date Added: 12/14/2018
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
Read More
KISD High School #6
KISD High School #6
Date Added: 11/30/2018
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
Read More
KISD High School #6

KISD Career Center students sit in on a review meeting.

KISD High School #6
Date Added: 11/26/18
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
Read More
KISD High School #6

Artist Rendering Of Main Entrance

KISD High School #6
Date Added: 11/02/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/2018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
KISD High School #6

Fine Arts Entrance

KISD High School #6
Date Added: 10/26/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
Evening rendering

Evening Rendering

KISD High School #6
Date Added: 10/19/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
  3. City of Killeen project introduction meeting took place 08/22/2018.
Read More
KISD High School #6

KISD #6 second Schematic Design board presentation.

KISD High School #6
Date Added: 10/12/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
KISD High School #6

Conceptual Building Main Entry

KISD High School #6
Date Added: 10/05/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
KISD High School #6

KHS staff reviews schematic plans and renderings.

KISD High School #6
Date Added: 09/14/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Design Charette was conducted 07/23/18 - 07/25/18.
Read More
KISD High School #6

First artist’s rendering of KISD’s new high school #6

KISD High School #6
Date Added: 09/07/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. Design Charrette was conducted on July 23rd – 25th.
Read More
KISD High School #6
KISD High School #6
Date Added: 08/24/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. Design Charrette was conducted on July 23rd – 25th.
  2. A general design direction was established and approved by the Charette committee.
Read More
KISD High School #6
KISD High School #6
Date Added: 08/17/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. Developing floor plans and site plans for the Schematic Design Department meetings.
Read More
KISD High School #6
KISD High School #6
Date Added: 08/10/2018
Current Phase: Schematic Design
Contractor: TBD
Read More
KISD High School #6

First artist’s rendering of KISD’s new high school #6

KISD High School #6
Date Added: 07/27/2018

Project Name: High School #6
Current Phase: Schematic Design
Contractor: TBD
1. CURRENT PROJECT STATUS
A. Programming sessions were conducted on July 11th and 12th

Read More