Date Added: 01/13/19
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • At the December Board Meeting, the Board of Trustees approved a change to the exterior design of the prototype building to be more equitable to the most recent KISD school designs. See attached.
  • Design Development documents are in production.
  • The design team met with all stakeholders to review the documents and provided valuable input.
  • The contractor for the project, Cloud Construction, has been providing input to the design team on constructability and cost management.
3 Clifton Park/Bellaire
  • At the December Board Meeting, the Board of Trustees approved a change to the exterior design of the prototype building to be more equitable to the most recent KISD school designs. See attached.
  • Design Development documents are in production.
  • The design team met with all stakeholders to review the documents and provided valuable input.
  • The contractor for the project, Cloud Construction, has been providing input to the design team on constructability and cost management.
4 East Ward/West Ward
  • Design Development documents are in production.
  • The contractor for the project, Bartlett Cocke Construction, has been providing input to the design team on constructability and cost management.
5 ADA/TAS Improvements (handicap accessibility)
  • Design Development documents for Packages 1 & 2 are in production.
6 Safety and Security
  • Construction Documents for Packages 1 & 2 are in production.
7 Elementary School 36
  • KISD is evaluating options for a potential site for another new elementary school in the district.