Date Added: 11/30/2018
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • Schematic Design was presented to the Board of Trustees on Tuesday. Board members provided valuable feedback and expressed positive support for the design of the building. The project goes to the board on Dec. 11 for approval of the Schematic Design phase.
  • The contractor for the project, Cloud Construction, has been providing input to the design team on constructability and cost management.
  • Geotechnical borings and analysis are complete and the engineer is currently working on the report.
3 Clifton Park/Bellaire
  • Schematic Design was presented to the Board of Trustees on Tuesday. Board members provided valuable feedback and expressed positive support for the design of the building. The project goes to the board on Dec. 11 for approval of the Schematic Design phase.
  • The proposals for the contractor have been received and are currently under evaluation.
4 East Ward/West Ward
  • The design team continues to refine the project design and work through big picture details of the site and floor plans.
  • The selection of the contractor for the project is slated to go to the Board of Trustees on Dec. 11. The district has chosen the Construction Manager at Risk delivery method which means the contractor will be on board during design and will provide valuable input to the design team on constructability and cost management.
  • Geotechnical borings and analysis are complete and the report has been received from the engineer.
5 ADA/TAS Improvements (handicap accessibility)
  • KISD has refined the list of potential items to be addressed within the bond budget. The design team is working on outlining the road map for the project moving forward.
6 Safety and Security
  • The design team is hard at work developing the bid documents for the project which includes fencing at every academic campus that doesn’t currently have the standard layout and shade structures at all elementary schools that do not currently have two shade structures.
7 Elementary School 36
  • KISD is evaluating options for a potential site for another new elementary school in the district.