Killeen High School Renovation & Modernization

Killeen High School Renovation
Killeen High School Renovation & Modernization
Date Added: 09/07/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. First day of the Design Charrette was conducted on 06/30/2018.
  2. Second day of the Design Charrette was concluded on 08/16/2018.
  3. City of Killeen introduction meeting took place 08/22/2018.
  4. Schematic Design meetings with individual departments scheduled for Tuesday, August 28th, 2018.
  5. PBK is revising schematic floor plans based on departmental input.
  6. Mechanical systems introduction meeting took place 08/31/2018.
2. Upcoming Meetings
  1. Schematic Design department review meetings are scheduled for 09/12/2018
  2. Board of Trustees presentations of the schematic design are schedule for 09/18/18 and 10/09/18.
3. Issues/ Items Needing Attention
  1. N/A