1. Current Project Status
  1. First day of the Design Charette was conducted on 06/30/2018.
  2. Second Day of the Design Charette was concluded on 08/16/2018.
  3. City of Killeen introduction meeting took place 08/22/2018.
  4. Schematic Design meetings with individual departments took place 08/28/2018.
  5. PBK is revising schematic floor plans based on departmental input.
  6. Mechanical systems introductions meeting took place 08/31/2018.
  7. Schematic Design presentation to KHS staff and student body representatives took place 09/10/2018.
  8. Schematic Design review meetings with individual departments took place 09/12/2018.
2. Upcoming Meetings
  1. Board of Trustees presentations of the schematic design are scheduled for 09/18/18 and 10/09/18.
3. Issues / Items Needing Attention
  1. N/A