Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 09/28/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK provided a preliminary massing study of a second design option to facilitate construction phasing and reduce cost. PBK is working on a layout for the corresponding floor plans. This layout will be submitted for KISD’s review by the middle of next week.
  2. The consultant’s walk-through field investigation occurred on 9/26. The information gathered is currently being compiled.
2. Upcoming Meetings
  1. Board of Trustees presentation of updated schematic design is scheduled for 10/09/18.
3. Issues / Items Needing Attention
  1. Classroom corridor at ramp, gym entry, site monuments, site features