Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 10/23/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Daniel presented 3 Floor plan options with associated cost depicting different ratios and scopes of New Build vs Renovation square footages for district consideration.
    Option 3A:
    • This option works around the classroom wings and the cafeteria and kitchen.
    • No additional portables needed
    • Cafeteria and kitchen functional throughout the entire construction until new one is built
    • Fine arts are all in except for dance studio. Dance studio is an alternate
    • Field House is an alternate
    Option 3B:
    • This option works around the classroom wings to eliminate need for portables
    • Existing cafeteria and kitchen will need to be offline during construction of the new one
    • Fine arts are all in except for dance studio. Dance studio is an alternate
    • Field House is an alternate
    Option 3C:
    • This option pushing the new classroom wing and cafeteria closer to the existing school
    • Will require demolition of existing classroom wing, cafeteria and kitchen all at the same time in order to build the new addition all at the same time
    • Will require portables to replace demolished classrooms
    • Existing cafeteria and kitchen will need to be offline during construction of the new one
    • Choir stays where it is existing and dance uses existing small gym. Only theater and Band in new addition
    • Field House is an alternate: this option has more components in the field house alternate than the other two options. Included in the alternate are the training room, small and weight rooms and wrestling room.
  2. PBK will further refine option 3C and provide an additional option that is strictly Interior Renovation.
  3. PBK and ACI will identify and propose possible areas to be designed and permitted for construction during summer ’19.
  4. PBK to propose boring locations for Geotech investigations.
2. Upcoming Meetings
  1. KISD Projects DD presentation 1 scheduled for 11/27/2018.
  2. KISD Projects DD presentation 2 scheduled for 12/11/2018.
3. Issues / Items Needing Attention
  1. N/A