Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 10/26/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK received direction to proceed with presenting Option 3C to the School Board.
  2. PBK provided a study reflecting a mostly interior renovation option for comparison.
  3. Option 3C requires the kitchen and cafeteria to be down for an extended period. The team is looking into the logistics of utilizing the Auxiliary gym as a cafeteria.
  4. PBK will prepare exhibits of possible seating layouts for review. Locations for a serving area will also be included.
  5. ACI and PBK are to identify scope of work that might be able to get done in Summer 2019.
2. Upcoming Meetings
  1. KISD Projects SD presentation 1 scheduled for 11/27/2018.
  2. KISD Projects SD presentation 2 scheduled for 12/11/2018.
3. Issues/ Items Needing Attention
  1. N/A