Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 11/02/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK received direction to proceed with presenting Option 3C to the School Board.
  2. PBK investigating temp kitchen/seating layout. Providing sketch for review on 11/02/2018.
  3. PBK providing initial baseball bleacher sketches for KISD review.
  4. ACI and PBK are to identify scope of work that might be able to get done in summer 2019.
  5. PBK revising SD animation video.
2. Upcoming Meetings
  1. PBK to meet with the City of Killeen on 11/02/2018 to discuss any concerns for summer 2019 scope of work.
  2. Projects SD presentation 1 scheduled for 11/27/2018.
3. Issues/ Items Needing Attention
  1. N/A
4. Upcoming Deadlines
  1. Interior & Exterior Preliminary Design due to the District on 11/07/2018.
  2. Final SD Presentation & Animation due to the District on 11/14/2018.
  3. KHS SD Board Presentation on 11/27/2018.