Date Added: 11/30/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Revising presentation as per comments from Board workshop.
  2. Revising animation as per comments from Board workshop.
  3. Scheduling design development meeting for Friday 12/14/18.
  4. Setting up Construction Documents to reflect 2 GMP’ s.
2. Upcoming Meetings
  1. Weekly project update conference calls scheduled for 2:00 PM on Fridays.
3. Issues/ Items Needing Attention
  1. N/A.
4. Upcoming Deadlines
  1. Sending updated SD presentation to KISD on Friday 12/14/18.
  2. KHS SD Board Presentation on Tuesday 12/11/18.