Date Added: 12/21/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK coordinating geotechnical proposal with Langerman Foster Engineering.
  2. PBK revising Athletics area per DD meeting on Friday 12/14/18.
  3. PBK revising Choir area per DD meeting on Friday 12/14/18.
2. Upcoming Meetings
  1. SD presentation and Board meeting rescheduled for Tuesday 01/08/19.
  2. Meeting with Asbestos consultant schedule for Wednesday 01/09/19.
  3. Second round of DD meetings - Date to be determined.
3. Issues/ Items Needing Attention
  1. Meeting with KHS Maintenance to be set up - Date pending.
  2. Draft of project schedule submitted for KISD review.
4. Upcoming Deadlines
  1. NA