Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 01/11/19
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Langerman Foster Engineering submitted proposal to KISD for review.
  2. PBK revising Floor Plans per DD meeting on Friday 12/14/18.
2. Upcoming Meetings
  1. Meeting with Asbestos consultant schedule for Wednesday 01/09/19.
  2. SD presentation and Board meeting rescheduled for Tuesday 03/05/19.
  3. Building systems finalization / net zero / PV meeting scheduled for 01/11/2019 at 10:00 AM.
  4. Second round of DD meetings to be set up - schedule to be coordinated with PBK & KISD.
3. Issues/ Items Needing Attention
  1. Meeting with KHS Maintenance to be set up - date pending.
  2. Draft of project schedule submitted to KISD for review.
4. Upcoming Deadlines
  1. NA