Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 01/11/19
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Additional Field Investigation scheduled for Monday, 01/21/19.
  2. PBK generating background drawings.
  3. Geotechnical Services pending Board of Trustees approval of Schematic Design presentation.
2. Upcoming Meetings
  1. Schematic Design presentation to the Board of Trustees rescheduled for Tuesday, 03/05/19.
  2. Second round of Design Development meetings to be set up - schedule to be coordinated with PBK & KISD.
3. Issues/ Items Needing Attention
  1. Meeting with KHS Maintenance to be set up - Date pending.
  2. Proposed Project Schedule has been reviewed by KISD on Tuesday, 01/08/19.
4. Upcoming Deadlines
  1. NA