Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 02/08/19
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. ACI reviewing cost estimate with alternates for Fine Arts and Athletics.
  2. Structural & MEP Consultants site visit schedule for Monday, 02/18/19.
  3. Geotechnical Services pending Board of Trustees approval of Schematic Design presentation.
2. Upcoming Meetings
  1. Schematic Design presentation to the Board of Trustees scheduled for Tuesday, 2/26/19.
  2. Second round of Design Development meetings to be set up - schedule to be coordinated with PBK & KISD.
3. Issues/ Items Needing Attention
  1. Meeting with KHS Maintenance to be set up - Date pending.
  2. Need meeting set up with Evan Leach to discuss temp kitchen - Date Pending.
  3. Evan Leach to identify what Food Services equipment will be required at the Bistro.
4. Upcoming Deadlines
  1. NA