Killeen High School Renovation & Modernization

Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 02/15/19
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. ACI provided cost estimate with alternates for Fine Arts and Athletics for District review.
  2. Structural & MEP Consultants site visit schedule for Monday, 02/18/19.
  3. Geotechnical Services pending Board of Trustees approval of Schematic Design presentation.
  4. PBK revising renderings to show images of KHS without alternates.
  5. Design and Construction schedule will be revised to indicate GMP 1 after KISD HS#6 total GMP is approved.
2. Upcoming Meetings
  1. Schematic Design presentation to the Board of Trustees rescheduled for Tuesday, 02/26/19.
3. Issues/ Items Needing Attention
  1. Meeting with KHS Maintenance to be set up - Date pending.
  2. Need meeting set up with Evan Leach to discuss temp kitchen - Date Pending.
  3. Evan Leach to identify what Food Services equipment will be required at the Bistro.
4. Upcoming Deadlines
  1. NA