Project Name: High School #6
Current Phase: Schematic Design
Contractor: TBD
1. CURRENT PROJECT STATUS
  1. Programming sessions were conducted on July 11th and 12th
  2. Design Charrette was conducted July 23rd - 25th
  3. A general design direction was established and approved by the charrette committee
2. UPCOMING MEETINGS
  1. Schematic Design meetings will be scheduled during the upcoming months
  2. Meeting at the City of Killeen, Commercial Plan Review division, will take place on August 22nd at 2:00PM
3. ISSUES/ITEMS NEEDING ATTENTION
  1. PBK to further develop options for the school entry design
  2. PBK to develop options for the exterior facade for classroom wings.