  1. Design Charrette was conducted 07/23-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
  3. City of Killeen project introduction meeting took place 08/22/2018.
  4. Mechanical systems introduction meeting took place 08/31/2018.
  5. Schematic Design Department follow up meetings took place 09/07/2018.
  6. Schematic Design presentation to KHS staff and student body representatives took place 09/10/2018.
  7. Mid Schematic Design presentation to Board of Trustees took place 09/18/2018
  8. Construction manager kick-off meeting with American Constructors took place 09/19/2018
2. Upcoming Meetings
  1. Board of Trustees presentation of schematic design is scheduled for 10/09/18.
3. Issues/ Items Needing Attention
  1. Chaparral curve / intersection with the City of Killeen and Bell County. PBK / Cunningham-Allen are contacting Bell County.