1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
  3. Schematic Design presentation and Board of Trustees approval took place 10/09/2018.
  4. DD department review meetings took place 11/15/2018.
2. Upcoming Meetings
  1. Weekly project update conference calls are scheduled for 2:00 PM Friday.
  2. City / County meeting is scheduled for 11/28/2018. Need to determine who will have jurisdiction over the north road and the timeframe for construction. AHJ is necessary prior to design of north road, pedestrian access, and potential traffic signals.
3. Issues/ Items Needing Attention
  1. NA.