KISD High School #6

KISD High School #6

Checking depth of test pit one

KISD High School #6
Date Added: 12/14/2018
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
  3. Schematic Design presentation and Board of Trustees approval took place 10/09/2018.
  4. DD department review meetings took place 11/15/2018.
  5. KISD / Bell County / City of Killeen / City of Harker Heights meeting regarding Chaparral Road took place 11/28/2018.
  6. Fine Arts meeting with Theater Consultant (Enrich Friend, Teqniqal) took place Monday 12/10/2018 at 9:00 A.M.
  7. Geotechnical report draft review meeting took place Tuesday 12/11/2018 at 9:00 A.M.
  8. On site test pits were excavated Tuesday 12/11/2018, facilitated by American Constructors.
2. Upcoming Meetings
  1. Weekly project update conference call is cancelled for Friday 12/14/2018.
  2. Geotechnical report draft review meeting is scheduled for Tuesday 12/11/2018 at 9:00 A.M. at the KISD Facilities Conference Room.
3. Issues/ Items Needing Attention
  1. PBK is coordinating with Cunningham – Allen to get a proposal to design the north road to city standards.
  2. Need Kitchen design review meeting when Killeen ISD Food Services Director is ready.