KISD High School #6

KISD High School #6

Fine Arts Entry View

KISD High School #6
Date Added: 01/11/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
  3. Schematic Design presentation and Board of Trustees approval took place 10/09/2018.
  4. DD department review meetings took place 11/15/2018.
  5. KISD / Bell County / City of Killeen / City of Harker Heights meeting regarding Chaparral Road took place 11/28/2018.
  6. Fine Arts meeting with Theater Consultant (Erich Friend, Teqniqal) took place Monday 12/10/2018 at 9:00 AM
  7. Geotechnical report draft review meeting took place Tuesday 12/11/2018 at 9:00 AM.
  8. On site test pits were excavated Tuesday 12/11/2018, facilitated by American Constructors. Langerman-Foster pit observation report was distributed 12/17/2018.
  9. Second draft geotechnical report was issued 01/08/2019.
2. Upcoming Meetings
  1. Building systems finalization / net zero / PV meeting scheduled for 01/11/2019 at 10:00 AM.
3. Issues/ Items Needing Attention
  1. North road proposal received from Cunningham – Allen and forwarded to Killeen ISD for review 12/26/2018.
  2. Need Kitchen design review meeting when Killeen ISD Food Service Director is ready.
Killeen Independent School District