KISD High School #6

KISD High School #6
KISD High School #6
Date Added: 01/25/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
  3. Schematic Design presentation and Board of Trustees approval took place 10/09/2018.
  4. DD department review meetings took place 11/15/2018.
  5. KISD / Bell County / City of Killeen / City of Harker Heights meeting regarding Chaparral Road took place 11/28/2018.
  6. Fine Arts meeting with Theater Consultant (Erich Friend, Teqniqal) took place Monday 12/10/2018 at 9:00 AM
  7. On site test pits were excavated Tuesday 12/11/2018, facilitated by American Constructors. Langerman-Foster pit observation report was distributed 12/17/2018.
  8. Second draft geotechnical report was issued 01/08/2019.
  9. ACI/ PBK/ Cunningham-Allen north road rough order of magnitude cost estimate sent 01/18/2019
  10. Killeen ISD / City of Killeen North Road meeting took place 01/23/2019.
  11. Food Service / kitchen design review meeting took place 01/24/2019.
2. Upcoming Meetings
  1. PBK Sports / Killeen ISD athletics review meeting scheduled for Wednesday 01/30/2019 at 10:00 AM at KISD Facilities conference room.
  2. Joint Killeen ISD / City of Killeen Workshop is scheduled for 01/31/2019.