Date Added: 02/08/19
Current Phase: Construction Documents
Contractor: American Constructors
1. Current Project Status
  1. KISD / Bell County / City of Harker Heights / City of Killeen meetings regarding Chaparral Road took place on 12/7/17, 5/30/18, 8/8/18, 11/28/2018, 01/23/2019, and 01/31/2019.
  2. PBK Sports / Killeen ISD athletics review meeting took place Wednesday, 01/30/2019 at 10:00 AM at KISD Facilities conference room.
  3. Construction Document 25% review compiled and submitted to KISD and ACI for review on Thursday, 01/31/2019.
2. Upcoming Meetings
  1. City of Killeen rezoning vote anticipated for Tuesday, 02/19/2019.
3. Issues/ Items Needing Attention
  1. Need kitchen layout feedback for plans sent on Thursday, 02/07/2019.
  2. Need Fine Arts Acoustic/AV review meeting with Bai.
  3. Need finishes meeting.
  4. Cunningham-Allen recommends another pre-development meeting with the City of Killeen (outside of regular Wednesday City Planning meetings).