News and Updates

KISD High School #6
KISD High School #6
Date Added: 11/30/2018
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 11/30/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Revising presentation as per comments from Board workshop.
  2. Revising animation as per comments from Board workshop.
Read More
General Updates
General Updates
Date Added: 11/30/2018
Item Update Items
1 General
2 Pershing Park/Sugar Loaf
  • Schematic Design was presented to the Board of Trustees on Tuesday. Board members provided valuable feedback and expressed positive support for the design of the building. The project goes to the board on Dec. 11 for approval of the Schematic Design phase.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 11/26/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Sent SD presentation to KISD for review.
  2. Sent updated animation to KISD for review.
  3. Identified summer 2019 scope of work and we are generating base files.
Read More
KISD High School #6

KISD Career Center students sit in on a review meeting.

KISD High School #6
Date Added: 11/26/18
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Construction manager kick-off meeting with American Constructors took place 09/19/2018.
Read More
KISD High School #6

Artist Rendering Of Main Entrance

KISD High School #6
Date Added: 11/02/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/2018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 11/02/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK received direction to proceed with presenting Option 3C to the School Board.
  2. PBK investigating temp kitchen/seating layout. Providing sketch for review on 11/02/2018.
Read More
KISD High School #6

Fine Arts Entrance

KISD High School #6
Date Added: 10/26/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 10/26/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK received direction to proceed with presenting Option 3C to the School Board.
  2. PBK provided a study reflecting a mostly interior renovation option for comparison.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 10/23/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Daniel presented 3 Floor plan options with associated cost depicting different ratios and scopes of New Build vs Renovation square footages for district consideration.
Read More
Evening rendering

Evening Rendering

KISD High School #6
Date Added: 10/19/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23/0018-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
  3. City of Killeen project introduction meeting took place 08/22/2018.
Read More
KISD High School #6

KISD #6 second Schematic Design board presentation.

KISD High School #6
Date Added: 10/12/18
Current Phase: Design Development
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
September 14, 2018 Meeting Minutes
October 05, 2018 - Meeting Minutes
Date Added: 10/05/18
Item Update Items
1 General
2 Pershing Park/Sugar Loaf/Bellaire
  • After further analysis of student capacity needs, KISD chose to change the design of the Pershing Park/Sugar Loaf/Bellaire project to a 2-story 1,050 student facility. The schedule for the project is being revised based on a Fall 2021 opening date.
Read More
KISD High School #6

Conceptual Building Main Entry

KISD High School #6
Date Added: 10/05/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
September 28, 2018 - Meeting Minutes
September 28, 2018 - Meeting Minutes
Date Added: 09/28/18
Item Update Items
1 General
2 East Ward/ West Ward
  • The design team presented the Schematic Design package to the Board of Trustees. Board members provided valuable feedback and expressed strong support for the design of the building.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 09/28/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. PBK provided a preliminary massing study of a second design option to facilitate construction phasing and reduce cost. PBK is working on a layout for the corresponding floor plans. This layout will be submitted for KISD’s review by the middle of next week.
Read More
Killeen High School Renovation & Modernization
Killeen High School Renovation & Modernization
Date Added: 09/28/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Design Charrette was conducted 07/23-07/25/2018.
  2. Initial Schematic Design Department meetings took place 08/21/2018.
Read More
Killeen High School Renovation

KHS staff reviews schematic plans and renderings.

Killeen High School Renovation
Date Added: 09/17/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. First day of the Design Charette was conducted on 06/30/2018.
Read More
September 14, 2018 Meeting Minutes
September 14, 2018 Meeting Minutes
Date Added: 09/14/18
Item Update Items
1 General
2 Pershing Park/ Sugar Loaf /Bellaire
  • The design team met with district leadership to review options and determine a palette for the interior materials and colors.

Read More
KISD High School #6

KHS staff reviews schematic plans and renderings.

KISD High School #6
Date Added: 09/14/18
Current Phase: Schematic Design
Contractor: American Constructors
1. Current Project Status
  1. Design Charette was conducted 07/23/18 - 07/25/18.
Read More
KISD High School #6

First artist’s rendering of KISD’s new high school #6

KISD High School #6
Date Added: 09/07/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. Design Charrette was conducted on July 23rd – 25th.
Read More
Killeen High School Renovation
Killeen High School Renovation & Modernization
Date Added: 09/07/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. First day of the Design Charrette was conducted on 06/30/2018.
Read More
KISD High School #6
KISD High School #6
Date Added: 08/24/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. Design Charrette was conducted on July 23rd – 25th.
  2. A general design direction was established and approved by the Charette committee.
Read More
Killeen High School Renovation
Killeen High School Renovation & Modernization
Date Added: 08/24/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. First day of the Design Charrette was conducted on July 30th.
Read More
KISD High School #6
KISD High School #6
Date Added: 08/17/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. Developing floor plans and site plans for the Schematic Design Department meetings.
Read More
Killeen High School Renovation
Killeen High School Renovation & Modernization
Date Added: 08/17/18
Current Phase: Schematic Design
Contractor: TBD
1. Current Project Status
  1. First day of the Design Charrette was conducted on July 30th.
Read More
Bond Program Is Well Underway
Bond Program Is Well Underway
Date Added: 08/10/2018

The Killeen ISD’s Bond Program is well underway, on budget and in some cases, projects have moved up in schedule. In May 2018, this community overwhelmingly authorized the school district to invest $426 million...

Read More
KISD High School #6
KISD High School #6
Date Added: 08/10/2018
Current Phase: Schematic Design
Contractor: TBD
Read More
Killeen High School Renovation
Killeen High School Renovation & Modernization
Date Added: 08/10/2018
Current Phase: Schematic Design
Contractor: TBD
1) Current Project Status
  1. Design Charrette was conducted on July 30th.
  2. Second day follow-up of Design Charrette will be on August 16th.
Killeen High School Renovation
Killeen High School Renovation & Modernization
Date Added: 08/03/2018

Project Name: Killeen High School Renovation & Modernization
Current Phase: Construction Administration
Contractor: TBD

Read More
August 02, 2018 Meeting Minutes
August 02, 2018 Meeting Minutes
Date Added: 08/02/2018
Item Update Items
1 General
2 Pershing Park/Sugar Loaf/Bellaire
  • Site survey field work is complete. The design team is starting to utilize the information for laying out the site design.
Read More
KISD High School #6

First artist’s rendering of KISD’s new high school #6

KISD High School #6
Date Added: 07/27/2018

Project Name: High School #6
Current Phase: Schematic Design
Contractor: TBD
1. CURRENT PROJECT STATUS
A. Programming sessions were conducted on July 11th and 12th

Read More
July 27, 2018 Meeting Minutes
July 27, 2018 Meeting Minutes
Date Added: 07/27/2018

Item Update Items
1 General
  • The East Ward/West ES and Pershing Park/Sugar Loaf/Bellaire ES projects are off and running! Nearly two dozen members of KISD leadership kicked the Huckabee team off with an inaugural project review session for the two projects...

Read More